Project Progress

Reimagining the Heart of the Home

By November 4, 2026No Comments

This thoughtfully designed renovation will transform the home’s main living spaces, creating a more open, functional, and inviting environment that better supports everyday living and entertaining. The project includes relocating the kitchen to the former dining room, where a reimagined layout will feature custom-style cabinetry, a spacious island, quartz countertops, a plaster-finished range hood, updated lighting, and carefully considered architectural details. A new pantry will provide additional storage and functionality, while the former kitchen will become a dedicated dining room with improved flow and a new multi-slide door connecting the interior to the outdoors.

Structural modifications will create a more seamless connection between the dining and living areas, with new flush beams replacing existing dropped beams and columns. Additional improvements include refinished hardwood flooring, updated lighting, fresh finishes, and enhancements to the foyer, laundry room, and mudroom. Outdoors, a new deck with cable railing and a dedicated gas connection for grilling will extend the home’s living and entertaining space.

Throughout the renovation, MOSAIC will bring together thoughtful space planning, quality craftsmanship, and cohesive design details to create a home that feels refreshed, beautifully connected, and tailored to modern living.

Before photos:

3D Renderings:

Oct. 15th: Covering and protection started today. MOSAIC sign and permit box were installed. Fridge, washer and dryer were staged. Microwave, dishwasher, and upper cabinets in laundry room will be staged in hallway tomorrow. Silt fence will be installed tomorrow. Framing package was ordered today as well.

Oct. 19th: Interior demo started today and will continue tomorrow. Brick demo will begin on Wednesday. Lumber package is scheduled to be delivered tomorrow. City site inspection is scheduled for tomorrow as well. We were also informed that the sliding glass door is scheduled to ship from the manufacturer on 11/16.

Oct. 22nd: Brick demo continued today and should finish up tomorrow. Roof shingle patches are scheduled for tomorrow. We met with the flooring foreman to check the condition of the subfloor and transitions.

Oct. 27th: Interior framing continued today and will tomorrow as well.

Nov. 2nd: We met with the framing foreman to discuss the kitchen window framing. After that, we created the rough mockup setup for the window. Framers are coming tomorrow to make window and sliding glass door framing adjustments. We also met with our project lead and the cabinet contractor to finalize the cabinet layout so production can begin.