This project located in Dunwoody encompasses a comprehensive kitchen addition and main-level renovation designed to improve flow, function, and architectural cohesion. The existing kitchen and powder room will be removed to accommodate a structural reconfiguration, including new beams, foundational supports, and an expanded rear exterior wall with updated siding, brick accents, roofing, windows, doors, and gutters. Deck modifications and new exterior stairs and landing will integrate the addition seamlessly with the outdoor space. Hardwood floors will be laced in and refinished throughout the main level for a cohesive finish.

The new kitchen will feature semi-custom cabinetry with integrated storage solutions, quartz countertops, upgraded appliances and plumbing fixtures, custom millwork, and layered lighting. Adjacent living areas will be opened by removing a load-bearing wall to create a more connected layout, complemented by new trim, lighting, and paint throughout. Additional updates include a renovated laundry room, relocated garage entry, and a newly constructed powder room, resulting in a cohesive, elevated transformation of the home’s main level.

Before photos:

3D Renderings:

January 12th: Interior protection installed. Silt fencing and tree save will be continued tomorrow.

January 22nd: Interior Demolition started a few days ago and moving along nicely. Concrete crew is scheduled to come either tomorrow after lunch or Thursday to dig footing so helical piers can be installed Friday weather permitting.

January 28th: Footing poured today and block installed as well. Framing set to start early next week.

February 5th: Framers had another productive day. Should have delivery date for flitch plate metal Monday.

February 11th: Framing continues. HVAC guys worked today. Plumbers are scheduled to start tomorrow. Making great progress.

February 13th: Bernie and Nathan leveled the dirt in the back yard and spread some pine straw. Framing continues.

February 20th: Framers got the interior framing completed today. New beams with flitch plates were installed today and header above the back door moved up into the ceiling.

March 3rd: Insulation went in today. Inspection is tomorrow. Incredible progress!

March 9th: Framers came back today and finished up all they needed to inside. Installed door to garage in laundry and removed old door as well. Installed last few pieces of sub floor and installed pocket door track.

March 12th: Drywall finishing started today will continue over the next few days. Nate also put blocking in for floating shelves.

March 13th: Ira and Sorrell did a mock up of the hood for the client to visualize the scale and proportion.

March 19th: Tile grouted in laundry room today. All wood flooring installed - ready to start sanding and finishing tomorrow.