Project Progress

Rest & Retreat Renovation

By February 17, 2026June 1st, 2026No Comments

This Atlanta renovation focuses on reconfiguring key living spaces to improve flow, function, and comfort. In the hallway and secondary bedrooms, we’re relocating doors, reframing walls, updating electrical and HVAC as needed, and refinishing all hardwood floors to create a cohesive, seamless look throughout. New solid-core doors, updated trim, recessed LED lighting, and fresh paint will elevate each space while maintaining continuity with the existing home. Smoke and carbon monoxide detectors will also be updated to meet current code requirements.

The Jack-and-Jill bath, primary suite, and closets are being fully transformed with new layouts, custom framing, and thoughtfully selected finishes. Both bathrooms will feature new porcelain tile, frameless glass shower enclosures, quartz surfaces, updated plumbing fixtures, modern lighting, and custom vanities. The primary bath will include a curbless shower, heated towel bar, and upgraded detailing for a more luxurious feel. Closet spaces are being reframed and enhanced with new doors, lighting, and a custom closet system in the primary suite. Throughout the renovation footprint, walls, ceilings, trim, windows, and doors will be freshly painted to complete a cohesive, high-end finish.

Before photos:

3D Renderings:

Jan. 22nd: Demo completing. Some framing started today.

Feb 9th: Electric rough continues, framing complete.

Feb 27th: Drywall finishing continued today. They actually may finish Monday or Tuesday. Tile prep will start Monday afternoon in the primary bathroom. We were able to move that up a couple of days and be ready for the layout on Wednesday. The cans were cut in and wired. They will be installed at trim out. The window didn’t make it in today but will be installed Monday afternoon.

March 23rd: Quartz tops installed today. J&J floor installed as well. The hardwood floors were finished on Saturday.

April 2nd: Installation of custom vanities.

April 17th: Paint finished today. May return Monday for touch ups after electric finishes trim out tomorrow. Electric trim started today as well as a good dent into the punch list.

April 24th: Bath accessories installed.

April 29th: Punch list completed today. Cleaning tomorrow!

April 30th: Cleaning done today. Signs and materials removed. A couple of touch ups completed. Shower handle replaced in J&J.

Check back for more updates!