Project Progress

The Ultimate Bath Upgrade

By March 24, 2026June 1st, 2026No Comments

This Dunwoody project is designed to elevate both function and comfort across the kitchen, primary bedroom, and a fully reimagined primary bathroom. In the kitchen, the existing gas setup will be removed and transitioned to a modern induction system, supported by updated electrical and a custom wood-framed oven surround for a seamless, built-in look. The primary bedroom will also be refreshed, including drywall repairs from a relocated doorway and a full repaint of all surfaces to create a cohesive, polished retreat.

The primary bathroom will undergo a complete transformation, taken down to the studs and thoughtfully rebuilt with a new layout that prioritizes both luxury and efficiency. The space will be reconfigured with newly framed walls, a relocated entrance, and a pocket door to improve flow. High-end features will be integrated throughout, including a spa-like shower with a center drain and herringbone tile floor, a custom bench and niche, heated floors, a heated towel bar, and a frameless glass enclosure. A new window will introduce natural light, while upgraded electrical, plumbing, and HVAC systems will enhance comfort and performance. Finished with custom vanities, slab surfaces, detailed millwork, and a cohesive paint palette, the result will be a refined, highly functional space tailored for everyday living.

Before photos:

March 16th :Protection complete upstairs and on main level.

March 20th: Demo was completed that doesn’t involve load walls and we are ready for framing Monday.

April 2nd: We passed combo rough inspection yesterday and insulation inspection today. Moisture barrier and accessory wall blocking is in place and ready for drywall Monday.
The siding was patched yesterday and the pad area was prepped for the generator today.

April 13th: Tile layout was agreed on and shower wall tile began.

April 27th: Tile was grouted today and the threshold area prepped for the new custom threshold. Trim should go mostly in tomorrow since we can’t finish due to the cabinets not being in yet.

May 12th: Vanity countertop installed today. Painting continued. HVAC trim out completed today. Gas line removed from kitchen cabinet, registers installed, and generator gas line installed. Electrical trim out will start in the morning. And paint should conclude tomorrow. Plumbing trim out scheduled for Thursday.

May 19th: Plumbing and mechanical inspections passed today. I’ll schedule electrical again with final building next week after doors and drawers and shower glass is installed. Water closet window got temper film applied today and the shutter installed on the window. Protection was removed as well. Touch ups and patch is scheduled for tomorrow. Cabinets will finish Thursday morning and Final cleaning is scheduled for Thursday afternoon.

Check back for more updates!